On December 17, 2021, the last train left Orangeville. Crews had already started pulling up track at the Veterans Way end of town that summer. The railway that ran out that day had belonged to the Town of Orangeville since September 29, 2000. Not many towns can say they owned a railway. Fewer can say they owned one for 21 years and then sold it to become a trail.
To understand why a town of 30,000 would buy 55 kilometres of track, you have to go back to when the track built the town.
Narrow gauge
In 1871 Orangeville was a mill village of about 1,450 people. That September the Toronto, Grey and Bruce Railway arrived from Toronto by way of Weston and Bolton. It was narrow gauge, three feet six inches between the rails, which was cheaper to build over the hills and cheaper to run. By December it reached Mount Forest. In August 1873 a second line opened north to Owen Sound, and in November 1874 the western line reached Teeswater. Both split at Fraxa Junction, just northwest of town.
So within three years Orangeville went from no railway to a junction, with trains to Toronto, to Georgian Bay and out to the farms of Bruce County. The village became a town on January 1, 1874.
In December 1879 a second company arrived. The Credit Valley Railway came up from Streetsville through Brampton, Cheltenham and Inglewood, crossed the Forks of the Credit on a trestle finished that September, climbed past Cataract and Alton, and met the TG&B at Melville Junction, south of town, where the two lines crossed in an X. It had its own branch west from Cataract to Elora, too. By 1881 the TG&B had been converted to standard gauge, and by 1884 the Canadian Pacific had taken over both.
The lines through time
A sketch map, not a surveyA junction town
For the next half-century the railway was Orangeville's reason for being bigger than its neighbours. It was the CPR's divisional point for the Bruce Division, the home terminal where crews changed and engines were serviced. The yard was expanded in 1906, a new station went up on Townline in 1907, and a five-stall roundhouse followed in 1926.
There's a lovely bit of family history in here, too. Orange Lawrence, the miller the town is named after, had a grandson named Orange Jull, and in 1884 Orange Jull patented a rotary railway snowplough: a big spinning wheel of blades on the front of a locomotive that throws snow clear of the track instead of shoving it aside. If you've ever seen a photo of a train blasting a white arc through a drift, that's the idea. Railways in snow country still use it.
The curve
The TG&B's route from Bolton climbed the Niagara Escarpment north of Cardwell, near where Horseshoe Hill Road and Escarpment Sideroad are today, and to get up the slope it bent back on itself in the Horseshoe Curve: an 11- to 12-degree curve with a 462-foot radius, partway up a 4.5-mile grade averaging 1.8 per cent.
On September 3, 1907, a special from Markdale to Toronto, packed with about 600 people heading to the Exhibition behind engine 555, came down the grade and left the rails on the curve. Seven people were killed and 114 injured. Speed was the suspected cause; the engineer and conductor were acquitted that November. The CPR had talked about closing the line as early as 1891 and surveyed a re-route in 1897 that was never built. The curve stayed in service until July 18, 1932, when the Bolton–Melville line was abandoned. The steel came out the next year, and Orangeville's trains to Toronto ran south through the Credit Valley from then on.
Fading out
The rest is a long, slow subtraction. Passenger service ended on the Elora branch on June 1, 1957, and through Orangeville in 1970. The station closed in 1983. The Teeswater line was abandoned in 1988 and the Elora branch was torn up around the same time. On October 31, 1995 the last freight ran to Owen Sound, and that line was formally abandoned in December.
That left one line: south through Melville, the Forks of the Credit and Brampton to the CP main line at Streetsville. And CP wanted out of that one too.
The purchase
When CP announced it would abandon the line, the town's shippers had a problem and the town had a choice. On September 29, 2000, the Town of Orangeville bought the 55 kilometres from Streetsville Junction to Orangeville through a company it wholly owned, the Orangeville Railway Development Corporation. Cando ran the trains until 2018. A group of local shippers, the Orangeville Brampton Rail Access Group, put more than $13 million into the line over 21 years. The town's own cost ran to roughly $450,000 a year.
For a while it was a romance. From the fall of 2004 the Credit Valley Explorer ran excursion trains out of Orangeville, down through the Forks of the Credit to Snelgrove or Inglewood, so you could see the valley the way the 1879 passengers did. A small replica station was built at the old yard for the people boarding it. The Explorer's last trips were in February 2018. When Cando's contract ended that June, the new operator, Trillium Railway (later GIO Railways), ran freight only, and the Explorer's three coaches were sold to the Waterloo Central Railway.
Freight was thinning out anyway. The line started with five customers in Orangeville and two in Brampton. By late 2021 it had three. The busiest, Clorox's Glad plant, took out its spur in November 2021. The shippers' group had already given notice in December 2020 that it would end its agreement at the close of 2021. Council directed the railway company's board to sell or lease what it had. On December 17, 2021, the last train left.
The path
The Orangeville yard was torn up in March 2022. Brampton bought about five acres of the corridor downtown for $24.25 million. In July 2022, Peel Region, Brampton, Caledon and Mississauga bought about 51 kilometres of it, from the Caledon–Orangeville boundary to just north of Streetsville, for $5.8 million, paid from Peel's fund for securing green space. It's all meant to become trail. Caledon's 36 kilometres are in preliminary design, with a public review set for late November 2026. Mississauga's first 1.15 kilometres are due to open in summer 2027. Brampton's stretch is still at the visioning stage.
Orangeville's own piece is further along. The second phase of the town's rail trail, about two kilometres from Broadway to Town Line, is due to finish in early November 2026. To the north and west the old lines are trails already: the Dufferin Rail Trail runs 38.1 kilometres from Orangeville to Dundalk through Shelburne and Melancthon, Grey County's CP Rail Trail carries on 77 kilometres to Owen Sound, and the Elora Cataract Trailway follows the old Credit Valley branch for 47 kilometres.
The arithmetic is hard to argue with. A line with three customers costs a small town a lot of money, and a trail costs much less and serves everyone. But it's worth sitting with this: in 1911, Orangeville had 2,340 people and trains in four directions. In 2026 it has more than 33,000 people, a weekday GO bus to Brampton, and Highway 10. The town got bigger and its railway got smaller until it was gone, and most of the commuters who made it bigger drive.
The station is still here. The 1907 building was moved to 35 Armstrong Street in 1989, reopened as an antiques shop and tea room, and now it's a restaurant and pub called Barley Vine Rail Co. You can have a pint where people used to buy tickets to Owen Sound. Then you can walk out to the rail trail and follow the line south, on foot, the way it went.